Import Estimate from Excel |
Top Previous Next |
* For use with the Scheduling module. Scheduling tasks may be imported first into the job detail items from an Excel Spreadsheet. Then within the Scheduling module, the tasks can be imported from the Job Cost module into the Schedule.
Job Cost Phase Settings This part of the screen is dynamic and will change depending on which option you choose.
•Use G/L Accounts - This may be used by companies that have set up their phase master list without using the decimal place of the phase to denote the sub-categories of labor, material, etc. Instead, you will utilize a g/l account to denote these categories. If you select the 'Use G/L Accounts' option, then you will be allowed to enter the general ledger account that should be associated with that column.
•3300.00 - Concrete with the labor amount and g/l account for labor •3300.00 - Concrete with the material amount and g/l account for material
• Job Cost Accounts - If you selected 'Use G/L Accounts' as noted above, then you can filter the list for only those accounts that have been set as direct cost accounts in the Chart of Accounts. Click the box 'Job Cost Accounts' to enable this filter.
•Job Cost Phase Increment - If the 'Use G/L Accounts' box is not checked as noted above, then this field will be visible. This may be used by companies that have set up their phase master list to utilize the decimal position of the phase to denote labor, materials, equipment, etc.
For example, any phase ending in .00 would represent the master phase (ie. 3300.00 - Concrete). Any phase ending in .10 represents labor, any phase ending in .20 represent material, etc. The 'Job Cost Phase Increment' option lets you assign the decimal increment number to be used for that specific column on the spreadsheet. In this scenario, the increment number would be 10. In your spreadsheet, the master phase number would have its own column (such as Column A) and would be mapped to the job cost phase field. The labor and material costs columns would be mapped to the estimated cost field. In this scenario, the increment on the cost columns would all be set to 10. The system would then create two items during the import process:
•3300.10 - Concrete with the labor amount •3300.20 - Concrete with the material amount
•Job - Single Job - Select the job number that the data will be imported into. The job number does not have to be in the spreadsheet in order to import into a single job. •Job - Multiple Jobs -
●If the Job field is one of the field mappings in the estimate import template layout, then the job number from the JOB column of the spreadsheet will be used as the target job number for each detail item that is created. If there is no job field in the field mappings list, then the target job will be pulled from the Job setting in the Job Info Group Box at the top left of the screen.
●All the Jobs in the job import file MUST already exist on the Job List. You will NOT be able to import estimate items on jobs that have not been set up in AccuBuild. If any jobs do not exist, then the posting process will display a list of missing jobs and then the posting will be canceled until the jobs are added. NOTE: You can use the Job List button in the Job Info Group Box to add new jobs if needed.
●When multiple jobs are involved in the import, the item numbers will be automatically numbered for the next sequential item number for each specific job.
•Trans Date - Typically this would be the date of the contract or the change order. All items imported will be updated with this date. •Change Order Work - If the spreadsheet data represents a change order, then be sure to select the Change Order Work field and enter the change order approval date. The change order status will then be updated in AccuBuild automatically. •Contr Ret % - If the imported estimate data includes amounts for contract billings, then you should set up the retention percentage on the contract using the Contr Ret % field. •Sub Ret % - If the estimate involves subcontractor payment amounts then the default retention percent for subcontractors should be set up using the Sub Ret % field.
•Round Amounts to Nearest Dollar - Use this option to round up all estimate amounts.
•Synchronize Job Cost & Billing Phases - Use this option to make the job cost phase and the billing phase the same on an item.
•Synchronize Item Desc & Billing Desc - Use this option to make the item descriptions and the billiing descriptions the same.
•Summarize Phase Totals - Use this option to summarize any records that contain the same job cost phase or billing phase.
•Ignore Zero Amount Items - If this option is checked, then the system will not post any item to the job detail file that does not have a billing amount or estimate amount or a unit amount. This will prevent the need to delete unnecessary lines from the work file. Note: If your file includes line items that are basically used for titles of section (ie. item 16000.00 Electrical is the section followed by sub-section 16000.01 Electrical - Labor, etc) then be sure to enter an amount in the unit field of the section title so that the line item will not be ignored during the posting routine.
•Keep ALL Master Phases - This option is used in conjunction with the Ignore Zero Amount Items checkbox. When this new checkbox is checked, then master phases (ending in .00) will NOT be removed even when the Ignore Zero Amount Items option is selected. This will allow you to import estimates with multiple amounts per cost code using the phase category feature without bringing in the zero amount phases within a group. The following example shows how the import estimate will work based on whether this option is checked:
Spreadsheet: Phase Phase Description Labor (01) Materials (02) Rentals (03) Other (04) 10.00 Mechanical 500.00 700.00 0.00 75.00
Import Results based on checkbox settings: NO Checkboxes checked 10.00 Mechanical 0.00 10.01 Labor 500.00 10.02 Materials 700.00 10.03 Rentals 0.00 10.04 Other 75.00
Ignore Zero Amount Items checked 10.01 Labor 500.00 10.02 Materials 700.00 10.04 Other 75.00
Ignore Zero Amount Items checked AND Keep All Master Phases checked 10.00 Mechanical 0.00 10.01 Labor 500.00 10.02 Materials 700.00 10.04 Other 75.00
•Mark All Items for Buyout - 'Buyout Items' refer to any type of goods or services on a job that you will be purchasing using an AccuBuild Purchase Order or Subcontract Order. These items are stored in the Job Cost > Update Jobs > Detail Items screen and be manually entered or imported into the job through the Import Job Estimate File option. As orders are created, you can simply pick the items to be purchased from a list of items that have been created for that specific job.
oIf importing the buyout items into the system along with regular budget items, then the spreadsheet should contain a separate column for the item type. The value of the item type should equal 1 in the spreadsheet whenever the row contains a buyout item. (The item description and item quantity columns on the spreadsheet can be used for either a budget or buyout item). If the items that you are importing are all buyout items then you can leave out this extra column and simply check the box labeled Mark all items for Buyout. An example of a spreadsheet containing only buyout items is located within the \AccuBld9\Samples folder. Be sure to also read the documentation in the Orders module for complete instructions and recommendations on importing buyout items.
Note: Business Rules were added to the estimate import process when importing Production Units by Detail Item to make sure duplicate Bid Item Numbers are not imported at the same time. Posting of the import records will be rejected if duplicate Bid Item Numbers are encountered.
Print the Job Detail Items - Item List Report from the Job Cost Reports Menu to view the imported records.
|