Create Contract Billing |
Top Previous Next |
•Client - Enter the client to be billed on the project. This field will be filled in automatically from the Owner field located on the Update Jobs > Billing Info Tab of the job list screen.
•Invoice No - An invoice reference number will be generated automatically. This invoice number must be unique, and can be changed if desired.
•Date - Enter the date of the billing.
•Billing Application Number - Enter the billing application number for the current job. The system should supply the next application number automatically. The application number represents how many times a billing has been generated for the project. The first billing on the job would have a billing application of "1", the second billing on the job would have a billing application of "2", etc.
•Desc - The system will provide a default billing description using a combination of the job number and the billing application number. The default description can be changed if desired, just remember that the description entered here will be stored as the transaction description for all related transaction files when the billing is posted through the system.
•Billing Period - Enter the beginning and ending dates for the billing period. These dates should represent the construction period that the customer is being invoiced for on the project.
•The AIA Format will contain an additional field for stored materials. You may not bill more than 100% of the item value.
•The unit billing format will only allow for the units completed-to-date to be entered. The amount completed-to-date on a unit billing will be extended automatically based on the unit price. You may over bill the contract quantities on a unit billing. This will allow projects to be billed more in line with state and federal projects where the scheduled units can end up over billed or under billed at the end of the project and simply adjusted at the end on the final billing. You will need to enable the option titled "Allow Completed Unit Overruns on Contract Billings" in the Job Cost > Properties screen in order to use this function. Important Note: For Work in Progress Schedule (WIP) reporting, you will want to adjust your contract amounts for overbillings in order to avoid accelerating the percentage of completion on the project.
The contract billing screen has a check box to manually 'Flag Billing as Retention' in circumstances where you cannot use the Auto Retention feature (see the Automatic Billing Options below). Normally a contract billing is flagged as retention only when the Auto Retn button is used. If you bill for partial retention, the invoice is not flagged as retention unless you check the 'Flag Billing as Retention' box. If the box is checked, the invoice will display on the aging schedule under the retention column and the entry is given a source 21 indicating a retention billing. The billing description will not reflect that it is retention unless you manually change the description before posting the invoice.
Fixed % Billings - The fixed percentage option will apply a constant percentage to all line items on the billing. For example, if you want to bill all line items at 75% complete, you would use this method. Enter the fixed percentage in the Fixed % field, and then select the Fixed % button. The system will extend all billing line items at the stated percentage.
Automatic Billing Options - Click on this button to select from the following options:
•Automatic 100% - Select this option to automatically bill all contract items at 100% less the retention percentage that were set up with each item.
•Automatic Retention - Select this option to automatically bill all contract items at 100% plus any retention amounts. If the job has not been billed out completely, it is recommended that the Automatic 100% option be carried out first, so that the retention billing will only include retention amounts.
•Automatic Schedule % - This option imports the percentage complete on each item from the Scheduling module.
•Automatic Sub Payment Sheet % - This option allows you to manually generate sub payment sheets first and then use those percentages of completion to update the current billing to the customer. The sub payment sheet percentage must be higher than the existing billing complete in order for the billing percentage to be updated.
•Automatic Job Cost % - This option will calculate the percentage of completion on each job cost phase that is linked to a billing phase. The calculation will divide the total costs, including open payables, by the total estimated cost to determine the percent complete. If the calculated percentage is more than the current percentage for that item on the billing, the new calculated percentage will be used to update the billing item. If the costs to date are more than 100% of the estimated cost, then 100% will be used.
•If there are multiple items on the billing with the same billing phase, the calculated percentage will be applied to each item on the billing. For example, if phase 1000.00 Mobilization is 73 % complete based on the job cost totals, and there are 3 billing items linked to billing phase 1000.00, all 3 billing items will be set to 73% so that the roll up overall total on phase 1000.00 of the billing should be 73%.
•Important Note on Linked Projects - If the job is linked to multiple jobs for contract status purposes, the user will be prompted during the percentage calculations to determine whether the individual job should be used for the calculations or if all linked projects should be queried for estimates and costs in order to obtain the total percentage of completion. This could be very useful where the contact is set up on one job number but the costs for different phases or buildings etc are tracked on separate job numbers.
• Automatic PO Buyout % - Use this option to compute the percentage of completion based on the vendor / subcontractor invoiced amount entered to date on the associated order line item. The percentage is calculated by dividing the invoiced amount by the order amount.
This feature is very useful for completing the ONLINE subcontractor payment process which handles submitting invoice amounts from the field, routing submitted amounts through the AccuBuild AP Approval Process and then submitting owner billings based on the approved subcontractor percentages.
|