Materials

Top  Previous  Next
1.To record the material that was used on that day, click New.

 

2.Choose the associated Category from the list.  The categories must be established on the job in the Project Management module before one can be selected on this screen.

 

ABM3_Material

 

3.Enter the description of the material used.

 

4.Enter the number of units used.

 

5.Enter the cost per unit.  

 

6.Select the unit of measure: Units, Pounds, Tons, Metric Tons, Yards, Cubic Feet, Feet, Inch, Meter, Decimeter, Centimeter, Gallon, Quart, Pint, Ounce

 

7.Enter additional information in the Notes as needed.

 

8.Click Save to record your entry.   Click on an entry to display the information in detail.  Click the Back button to return to the Field Reporting main menu.  

 

ABM3_MaterialList